This blog is dedicated to one's journey of building her first home in the world's most isolated continental capital city - Perth.
Saturday, 26 October 2013
Week 13 : Bricks Delivered (week 6)
Bricks,Window and Door Frames have finally been delivered to the site. I wonder when the brickies will be around to commence work? Definitely got my excitement going again..
Saturday, 19 October 2013
Week 9-12: Man Hole Installed (week 2-5)
The construction process has not progressed much for quite a while now. The excitement has definitely died down a little for me. Still waiting for the bricks to be delivered.
Good to see that the 2 man holes have been installed underneath the ground.
Thursday, 19 September 2013
Week 8: Slabs Down (Week 1)
What can I say? Conslabulation! *beaming with delight* It's definitely a significant milestone in house building. I am so stoked to see the concrete slab finally installed and it shouldn't be for too long before the house is completed, I am hoping end of January.
I wonder if this is considered a good job or not? I'm just going to trust Celebration Homes on this.
I think this is what they call "manholes" Correct me if I'm wrong. Definition from Wikipedia is " A manhole is the top opening to an underground utility vault used to house an access point for making connections or performing maintenance on underground and buried public utility and other services including sewers, telephone, electricity, storm drains and gas"
2 man holes required for this tiny house.
Next stage will be brick delivery and bricklayer commencement.
Saturday, 14 September 2013
Week 7: Footings
Parents are here to visit and looks like they've brought me some good luck. Finally some progress with the construction.
Seems like a very tiny platform.
footings are now set in and ready for the slab to go in next (pending on the weather again)
Consecutive rain for 7 weeks and looks like it's not going to change any sooner. This is by far one of the wettest winter I've witnessed in Australia.
Wednesday, 4 September 2013
Week 4-6: Still Raining
Week 6 and still no signs of consecutive sunny days. Hence, no progress with the construction. My anticipation and excitement is gradually wearing thin.
Tuesday, 13 August 2013
Week 2 & 3: Clouds and Rain
It's been raining non-stop for the past 10 days and so far no signs of sunny day till next Monday.
As duly noted, apart from the appearance of two steel containers, no progress has been made so far. 10 days of rain and 3 more to go. Who's the murderer here? The weather of course, cause it's killing my patience.
Saturday, 3 August 2013
Week 1: Earthworks
The weather has been looking very gloomy and wet for Perth the last two weeks. It was finally nice to wake up to a warm and sunny Saturday morning. In order not to waste such a beautiful weekend, as always, I took my bike out to cycle with my brother. Our usual cycle path was from our current rented property to the new land. Due to the wet season, I wasn't expecting much to happen as the construction process are usually delayed. But to my surprise, the builders has already started with the earthworks and it was awesome to see some changes to my once awful looking land. Still looks quite terrible with the pile of sand at the front but at least the vegetation has been cleared and the land has been leveled thus far. Glad I chucked my camera into my bike pouch, guess I had a gut feeling that the nice weather was a good omen.
Unfortunately the weather forecast for next week is not looking great, probably a few showers. The next step will be a critical one as they have to lay the concrete slab and footing as the foundation of the house. To have a sturdy mixture of concrete, the right amount of water is essential. Extra rainwater to the mixture will be a horrible idea. Don't think the builders will want to get the foundation of the house wrong. Shall be patient then!
Situated behind some warehouses.
Nicely leveled.
Such terrible looking bricks. Will paint the brick wall with white or cream colours!