Wednesday, 19 March 2014

Week 26-27: Lock Up Stage

Finally the windows are up and in the lock up stage. It wouldn't be too long before we have the pre-handover meetings and keys handover with Celebration Homes, hopefully by next Friday.The clock is ticking for me as I will need to vacate my current rental premises by 7th April 2014. Things in life never does turn out as planned sometimes. I was hoping that the rental agent could extend my lease for 2 more weeks to allow some time for me to get this house ready. Unfortunately, the owner was adamant and firm with the vacation date. Looks like I'll be living in the garage for the moment while the other contractors work on the house. I still have lots to be done before the house is completed such as airconditioning, lighting installation, painting, flooring, glass splashback and curtains.

I am glad the exterior look of my house turned out like how I imagined it to be. The external walls have been rendered and I hope when it's all painted, it'll look alright. I'm slightly worried about the colour choice I have made at the pre-start session. Cross fingers it won't be too horrible! 

Floor tiles and wall tiles installed in the ensuite bathroom. I will be choosing # Raw Cotton (Dulux Paint) for the internal wall painting. 

Vanity area in the ensuite bathroom

Bathroom 

Kitchen sink 

Wednesday, 5 March 2014

Week 25: Installation of Cabinets

What a turn of events! I was actually surprised to see some progress after a few days. Hopefully it won't be too long from now. Cross fingers and hope that I'll get my keys end of March =)

 #Antique Wiluna White selected and installed for the laminex kitchen cabinets

laundry sink and cabinet installed 

#Husk chosen for the front laminex cabinet

cabinet for the bathroom #oyster linea

cabinet for the ensuite bathroom #oyster linea 

ceiling and cornice installed 

cornices done

stock pile of ceramic wall and floor tiles - ready to go! 

a closer look of the selection I've made for the bathroom 
Wall tiles - Lanka Fashion Bone
Feature tiles - #3 Honeycomb
Floor tiles - Lanka M-637 #64 Cinnamon


bathtub and sinks delivered 

Tuesday, 4 March 2014

Week 23-25: Ceiling, Doors and Window Frames

We are at the 25 week mark now and unfortunately, we're not at the lockup stage yet. Looks like Celebration Homes has failed to deliver the 26 weeks promise of building time. I have sent them an email questioning about their building duration policy but there was no response. Apparently it is very typical of builders to avoid complaints like this. It's been 15 months since I've first signed the preliminary contract with them. The building process has been a long delayed one. I'm just at a stage whereby my patience is running really thin and I just want this process to be over and done with. 

Celebration Homes has been a very disappointing experience thus far. The only good feedback I have for them is the sales consultant whom I've dealt with at the beginning. He was very friendly and easy-going. But once the building contract has been signed, what he promised and what turned out to be are totally different scenarios. During this long painful process of waiting for things to happen, I have paid a tremendous amount of money for the overlapping weekly rental and land loan. I don't even know whether it's feasible to seek for any form of compensation. Well, I wonder if there's anything different that I can do apart from waiting. From their latest update, my house should be ready for pre-handover end of March. Shall wait and see! 

Master bedroom- White gyprock hardwall plaster on the wall. Smooth texture to the wall


2nd bedroom 


Bathroom



Entry door and window frame installed 

Kitchen and living area - Ceiling installed

Long corridor to the garage door

Saturday, 15 February 2014

Week 22: Float Stage

Looks like the building process is speeding up. The roof stage has been completed this week and it's proceeded with the plaster floating stage.



Installation of the plaster float (internal grey coat)

More plaster float 

Room 2 

roof timber and electrical wiring 

more roof timber and electrical wiring 


Tuesday, 11 February 2014

Week 18 - 22: Roof Timber

I'm starting to doubt if Celebration Homes could deliver their promise of completing the house in 4 weeks time. Highly unlikely the way I see it now. Still at the roofing stage. I shall wait and see if miracle will happen.






Wednesday, 8 January 2014

Week 15 - 17: Pending for Roofing

Approximately 9 more weeks to go until "Week 26" as promised by Celebration Homes that the building process will be completed. Timber has been delivered to the building site and the next step will be the roof. Can't wait =) 

Tuesday, 17 December 2013

Week 19 - 21: More Brickwork (week 12-14)

More bricklaying has been commenced. 

Relatives from Malaysia were here to visit Perth and all they wanted was to visit the half built house. I'm glad that there were at least something to show. 

study room interior 

 The living room, dining room and bedrooms. Partitioned walls have not been installed as yet. Surprisingly the house turned out to be slightly bigger than I thought it'll be. 

 Living area

The garage.